Explore the largest solar farms expected to come online in Texas and see all proposed solar projects on a map.
Last updated: July 2026
On this page, you can explore our database of planned solar farms in Texas. Each month, we track projects in development and update our list of the largest solar farms expected to come online in Texas.
As of July 2026, there are 851 solar farms in development in Texas, according to Cleanview's project tracker. Their total planned capacity is 199,388 MW. See also: operating solar farms in Texas→
Planned Projects
851
Planned Capacity
199,388 MW
Unique Developers
141
Map of planned solar farms in Texas. Marker size reflects planned capacity.
1,200 MW
Expected Online: November 2028
Location: Scurry, Texas
1,126 MW
Expected Online: June 2030
Location: Pecos, Texas
1,125 MW
Expected Online: June 2030
Location: Pecos, Texas
1,124 MW
Expected Online: June 2028
Location: Deaf Smith, Texas
Developer: Intersect Power
1,026 MW
Expected Online: July 2027
Location: Refugio, Texas
Developer: Intersect Power
1,022 MW
Expected Online: March 2029
Location: Taylor, Texas
837 MW
Expected Online: October 2026
Location: Navarro, Texas
Developer: Solar Proponent
808 MW
Expected Online: June 2026
Location: Upton, Texas
Developer: Unable to find
805 MW
Expected Online: April 2029
Location: Mitchell, Texas
363 MW
Expected Online: August 2026
Location: Haskell, Texas
Developer: Intersect Power
363 MW
Expected Online: August 2026
Location: Haskell, Texas
Developer: Intersect Power
219 MW
Expected Online: August 2026
Location: Jones, Texas
Developer: Lightsource bp
206 MW
Expected Online: August 2026
Location: Jackson, Texas
Developer: Crayhill Renewables
204 MW
Expected Online: August 2026
Location: Lamar, Texas
Developer: Nexus Ventures
50 MW
Expected Online: August 2026
Location: Live Oak, Texas
Developer: Vistra
397 MW
Expected Online: September 2026
Location: Refugio, Texas
Developer: J-Power USA
394 MW
Expected Online: September 2026
Location: Refugio, Texas
Developer: J-Power USA
318 MW
Expected Online: September 2026
Location: Lamar, Texas
Developer: Invenergy