Clean Energy and Storage
Project Tracker
We pull every major interconnection queue each day, then find the company developing each project.
- Planned solar
- 560 GW
- Planned battery storage
- 463 GW
- Planned wind
- 159 GW
- Developers identified
- 416
See which projects are likely to get built
Most projects in a queue never get built. A signed interconnection agreement is the best sign that one will: the developer has made it through the grid operator’s studies and agreed to pay for the upgrades it needs.
We track where every project stands in its queue. 52% of planned solar in the seven major queues has a signed agreement, from 76% in MISO to 42% in PJM.
MISO has the most planned solar with a signed interconnection agreement
Planned solar in each market's interconnection queue, GW
Find the developer behind every project
Four of the seven major queues don’t name a project’s developer. MISO lists the substation it connects to. ERCOT lists the company that filed, usually a project LLC like S&S Renewables, LLC.
We trace each project to the company building it, through interconnection agreements, FERC filings, state permits and developers’ own announcements. So far we’ve matched 3,345 planned projects to 416 developers.
| What the queue says | What you see in Cleanview | ||||
|---|---|---|---|---|---|
| Queue | Project | Company listed | Developer | Capacity | Interconnection agreement |
| MISO | J1060West Memphis - Keo 500 kV Line Tap, St. Francis County, Arkansas | None | Invenergy | 500 MW solar | Signed |
| PJM | AG1-125Marysville-Flatlick 765 kV, Madison County, Ohio | None | Savion | 400 MW solar | Signed |
| SPP | GEN-2021-070Hodgeman and Ford counties, Kansas | None | Engie | 504 MW wind | Signed |
| ERCOT | 24INR0258Zeissel Solar, Knox County, Texas | ZSS Power, LLC | NextEra Energy | 452 MW solar | Signed |
| ERCOT | 24INR0201Short Creek Solar, Wichita County, Texas | Wichita Solar I, LLC | TotalEnergies | 628 MW solar | Signed |
NextEra Energy and Invenergy have the most planned solar
Planned solar, GW, and the number of projects, top 10 developers
See every developer's pipeline
Each developer gets a profile with every project we’ve tied to it: where it’s filing, how big each project is, how far along it is in the queue and when it expects to come online.
NextEra Energy has 103 planned solar projects in 21 states. 82% of that capacity has a signed interconnection agreement.
Know the day a project moves
We check every queue each day and the EIA’s survey of planned plants each month. When a project enters a queue, signs its interconnection agreement or starts construction, it shows up in your feed.
Follow a developer, a market or a technology, and get the changes by email every day or every week.
Recent milestones
Solar, wind and storage projects of 100 MW or more
- November 11, 2026
Interconnection agreement
Arc Energy Storage, 206 MW battery storage
Valor Infrastructure Partners. Lamar County, Texas. Texas PUCT
- November 9, 2026
Construction started
Waller Solar I, 176 MW solar
REV Renewables. Lancaster County, Virginia. PJM queue
- November 9, 2026
Construction started
Dixon Solar, 140 MW solar
SunEnergy1. Jackson County, Ohio. PJM queue
- November 9, 2026
Construction started
Waller Solar I, 131 MW solar
REV Renewables. Lancaster County, Virginia. PJM queue
- October 29, 2026
Interconnection agreement
Big Field Solar Project, 506 MW solar
Invenergy. Foard County, Texas. Texas PUCT
- October 27, 2026
Interconnection agreement
Tall Saddle Solar Project, 264 MW solar
Apex Clean Energy. Kenedy County, Texas. Texas PUCT
Built for the companies that build, fund and supply projects
The same data answers different questions, depending on where you sit.
Developers
See where competitors are filing, how big their projects are and how far along each one is. Spot the counties and markets getting crowded before you file.
- Who else is building storage in my county?
- Which competitors signed agreements this quarter?
Investors
Size a developer's pipeline before a deal, and see how much of it is likely to get built. Track a market's buildout from queue to construction.
- How much of this developer's pipeline has an agreement?
- How much solar will MISO add by 2029?
Equipment makers and service providers
Find projects that will soon buy panels, batteries, turbines, transformers or construction services, and the developer to call.
- Which projects signed agreements in Texas this month?
- Who's developing the biggest projects in PJM?
Get our data through an API
Everything on this page comes through our API: each project’s capacity, status, location, developer and interconnection agreement, updated every day. Pull it into your models, your CRM or your GIS. Or download any table as a CSV.
GET /api/v1/projects?technology=Solar&status=Planned&developer=NextEra { "project_name": "MRR Solar", "developer": "NextEra Energy", "technology": "Solar", "capacity_mw": 500, "status": "Planned", "has_ia_signed": true, "operating_date": "2030-07-01", "county": "Pecos", "state": "TX", "source_table": "ercot_queue", "source_id": "30INR0053", ... }